General
The Snohomish County Workforce Development CouncilRequest for Proposal (RFP)for the selection of contractor(s) for WIA Title I-B Youth Program Services For Justice Involved Youth for the period of July 1, 2006 through June 30, 2007 is now available.
Attachments
All inquires related to the RFP are to be submitted electronically. E-mail inquires should be identified on the e-mail as "Youth Program Services For Justice Involved Youth RFP Inquiry" and send to Trina Miller .
Written questions will be responded to within 72 hours by posting in the Question and Answer section on this page.
Questions received after 5 p.m. on June 15, 2006 will not be answered.
Evaluation Process and Timelines
May 17, 2006 |
Public Notice. |
May 17, 2006 |
Request for Proposal (RFP) available on WDC Website. |
May 24, 2006 1:30 p.m.-3:30 p.m. |
Mandatory Bidders Conference |
June 15, 2006 Must be received by 9 a.m. |
RFP responses are due at Snohomish County Workforce Development Council. |
June 15, 2006 Must be received by 9 a.m. |
Letters of Commitment are due at Snohomish County WorkForce Development Council. |
June 23, 2006 |
Committee reviews and recommends proposals for awarding. |
June 27, 2006 |
Full Board reviews recommendations and approves awards. Bidder(s) notified. |
June 30, 2006 Must be received by 5:00 p.m. |
Documentation of Qualification is due for any awarded bidder(s) that does not have such documentation on file at the WDC. |
July 1, 2006 |
Contracts begin |
Questions & Answers
Q. So you can have a consortium and apply as a stand alone?
A. Yes, you can bid both ways.
Q. Is it a preference towards a consortium?
A. No.
Q. Why is there not a preference towards a consortium
A. For monitoring reasons, one contract is preferred.
Q. So the 40-50 new participants is in addition to currently enrolled participants?
A. Yes.
Q. So any youth not exited would count as new?
A. No, we only count participants once.
Q. For a consortium, we need to submit two sets of budgets or should we combine them?
A. Keep them separate. The staff can combine them if necessary for the rating teams.
Q. Should the cover page be for the lead applicant or for both?
A. For the lead applicant.
Q. You will be monitoring quarterly?
A. Yes, for all programs.